Dear All;
I am curently in Organization restructuring project ,where currently there is one company code ,in future additional 4 new company code will be created .
Below I am giving the list of issues where i need help.
1) Currently there are around 2 lacks open POs and contracts in old company code .
In some PO GR is been done but IR is not done
In some PO GR is partially done .
Our Customer needs to transfer all the open PO to new company code .
How can I transfer the PO where GR is fully or partially done ?
2) Numbers of Plants will be same as present .
some plants needs to be under new company code .
Hiow will it be done .
Thanks and Regards;
Joydeep Mukherjee